AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 10 AUGUST

Please see below an update on anticipated transport movements to facilitate the construction of WSIII wind farm.

Day Description WSIII HGV Movements
Monday

Aggregates and site equipment  

13
Tuesday

Aggregates and site equipment  

12
Wednesday

Aggregates and site equipment  

12
Thursday

Aggregates and site equipment  

14
Friday

Aggregates and site equipment  

14

These deliveries will be using the A713 and the WSIII site entrance. We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources.

Abnormal load deliveries to site. Tues 11 – towers and rotors x 6, Wed 12 – rotors and blades x 6, Fri 14 – towers and blades x 6. These components will be delivered in two consignments of three and are planned to leave King George V Port at 7pm and 12 midnight.

Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758