Please see below an update on anticipated transport movements to facilitate the construction of WSIII wind farm.
| Day | Description | WSIII HGV Movements |
| Monday | Aggregates and site equipment |
18 |
| Tuesday | Aggregates and site equipment |
18 |
| Wednesday | Aggregates and site equipment |
18 |
| Thursday | Aggregates and site equipment |
18 |
| Friday | Aggregates and site equipment |
18 |
These deliveries will be using the A713 and the WSIII site entrance. We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources.
Abnormal load deliveries to site. Tues 1 – towers and blades x 6, Wed 2 – towers and nacelles x 6, Fri 4 – nacelles not under police escort. These components will be delivered in two consignments of three and are planned to leave King George V Port at 7pm and 12 midnight.
Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758