AN UPDATE ON TRANSPORT MOVEMENTS TO AND FROM SITE W/C 5 OCTOBER

Please see below an update on anticipated transport movements to facilitate the construction of WSIII wind farm.

Day Description WSIII HGV Movements
Monday Aggregates and site equipment  

2
Tuesday Aggregates and site equipment  

5
Wednesday Aggregates and site equipment  

5
Thursday Aggregates and site equipment  

6
Friday Aggregates and site equipment  

6

These deliveries will be using the A713 and the WSIII site entrance. We expect these movements to take place between 7am and 7pm. There will be other smaller deliveries with site resources.

Abnormal load deliveries to site. Mon 5 – towers and blades x 3, Wed 7 – towers and blades x 3 (TBC), Thur 8 – blades x 3. These components are planned to leave King George V Port at 7pm and Ayr at 10pm.

Please note these traffic movements are subject to change due to operational delays. Apologies for any inconvenience caused. Please direct any queries to Cris Thacker on 07353 962 758